With Haliotis 2, one of the largest water treatment projects in France is currently being developed in Nice. Located between the Promenade des Anglais and the runways of Nice Côte d’Azur Airport, the groundwork for the new wastewater treatment plant is underway. Before the actual treatment facilities can be constructed, extensive deep foundation works along the existing dike structure are required. On the seaward side, a total of 82 stabilizing barrettes are being constructed as part of the project to prevent slope failure in the event of an earthquake. Along approximately 500 meters of the dike, deep-founded concrete elements are being constructed to secure the subsoil for the future treatment basins. FAYAT FONDATIONS has been commissioned to carry out these works. The project represents a total investment of around €700 million (including construction and operation) and places high demands on planning, technology, and on-site quality.
The stabilizing barrettes are constructed using diaphragm wall techniques. After excavation with a grab, a total of 82 barrette elements are desanded, followed by the installation of reinforcement cages made of reinforcing steel, which are placed and concreted at depths of up to 40 meters. Each structural element measures approximately 6.5 to 6.6 meters in width with a thickness of 800 mm. The reinforcement elements are manufactured from reinforcing steel, individually adapted to the project requirements, and form a stable connection between the subsequent concrete components.
A modern telescopic crawler crane, the SENNEBOGEN 6113 E, is used for the lifting and handling operations required on site. The crane is provided by SAML, a subcontractor of the FAYAT Group. It supports the work particularly in handling the reinforcement cages for the individual barrette elements.
This solution enables flexible and cost-efficient execution of the work under the given conditions. During installation, the cages are initially picked up horizontally, carefully raised into position, and then precisely placed into the prepared excavation sections of the barrette elements. Operators benefit from the ability to perform simultaneous movements and position components safely.
Thanks to its capability to travel with a suspended load and telescope the boom under load, the cages can be positioned safely even in confined space conditions. The full load capacity over 360° also allows loads to be moved independently of the upper structure orientation. These features ensure reliable application of reinforcement technology even under demanding conditions.
In addition to installing the reinforcement cages, the 6113 E performs all other lifting tasks on site. These include installing and extracting casing as well as handling equipment during the desanding of boreholes.
Particularly during the extraction of components, increased forces act on the machine and boom. Thanks to its stable design and robust crawler undercarriage, the crane reliably withstands these loads. Its advanced engineering has been tested for such applications and enables safe operation even under dynamic loads.
Even during repeated lifting operations under demanding conditions, the machine remains stable and precisely controllable. This allows construction teams to benefit from fast and safe execution of all tasks.
A particular challenge arises from the direct proximity to the airport. The maximum permissible boom height is limited by aviation regulations, placing specific demands on planning and safety on the jobsite. The crane used is equipped with an electronic height limitation system (“Virtual Wall”), which allows the permissible working area to be precisely defined. In addition, the boom tip is fitted with an aviation warning light for day and night operation. These systems ensure that all work is carried out strictly within the defined safety parameters. Especially under these conditions, the combination of controlled height limitation and full 360° load capacity enables safe and continuous workflows.
In daily jobsite operations, the SENNEBOGEN 6113 E supports both equipment setup and all lifting operations throughout the various construction phases. Thanks to its combination of load capacity, maneuverability, and precise control, it can handle multiple tasks without the need for additional machines.
The telescopic crawler crane has been in operation on various jobsites for around 18 months. Its flexibility and ability to move loads safely even under confined conditions are particularly valued. For construction companies, this represents an economical solution for efficiently meeting diverse jobsite requirements.
As a partner in modern lifting technology, SENNEBOGEN offers comprehensive consulting, detailed information on application possibilities, and a wide range of tested machine solutions. High-quality products ensure reliability, safety, and efficient operation on demanding construction sites worldwide.







Press inquiries: [email protected]
SENNEBOGEN
Maschinenfabrik GmbH
Sennebogenstraße 10
94315 Straubing